The Kimberton Road Bridge repair has been completed!


The road between Flint Road and Art School Road is now open to through traffic.


The paving of the overlay is scheduled for Tuesday, July 19*, at which time the bridge will be closed.


Updated: Mon, Jul 11, 2022 - 3:00 p.m. *Wed, Jul 13, 2022 - 12:19 p.m.


=============================================================

Our Public Works Department and contractors have been working tirelessly on the repair of the stone arch bridge on Kimberton Road.


They anticipate completion of the project to be early July.


Kimberton Road between Flint Road and Art School Road will remain closed with no through traffic permitted.


All residents directly affected by this closure have been sent letters noting the new end date to their home addresses via regular mail.


Updated: Wed, Jun 22 - 12:00 p.m.